Information about Charlemont Connect make-ready. Make-ready is work to prepare a “path” for the distribution network to run throughout the town. Most of this work is done by the utilities (National Grid and Verizon) to make space on existing utility poles. In some cases, the town may perform make-ready work by installing new underground conduit (e.g. near the town hall or on Hawk Hill Road) or new utility poles (e.g. on the west end of Tower Road) to create a cost-effective path for the distribution network.

2021.03.07 Select Board Update

Charlemont Municipal Fiber Network
Selectboard Status Report
March 7, 2021

Summary
Network construction is underway and the essential work in the village center has been completed to alleviate conflicts with the DOT traffic calming project, which will be resuming soon. The subscription website is operational and we are encouraging all residents to sign up so that WhipCityFiber can plan the installation schedule for the summer. There will be a virtual information session on March 16. Sign-ups are currently at 20%, mostly through word-of-mouth. The project remains on budget. WhipCityFiber is recommending a “safe” schedule with FSA01 (the first fiber service area) lighting up in July and the other FSAs following at two-month intervals. The town is working with WGE and TriWire to try to accelerate this schedule if possible. Currently, the lack of fiber splicing and testing crews seems to be the bottleneck.

Comments closed

Warner Hill Road Path Preparation Complete!

Danek Excavating and Burke Electric have completed the path preparation make-ready on Warner Hill Road! Underground conduit and two utility poles have been installed on a section of the road to allow the municipal fiber network to bypass a difficult to maintain section of aerial utilities that provides electrical and phone service to residents through the town of Heath.

Comments closed

Verizon Make-Ready Complete!

Finishing roughly seven weeks ahead of schedule, Verizon has now licensed the use of the utility poles on all seventeen applications to Charlemont’s municipal network! This completion accelerates the next steps in the process: the inspection and remediation of the make-ready work and the relocation of the state’s MBI 1-2-3 middle-mile network fiber.

Comments closed

2020.11.01 Select Board Update

Charlemont Municipal Fiber Network
Select Board Status Report
November 1, 2020

Summary
Verizon has now approved 14 licenses (out of 17), with just a few poles left on the other applications. This remains the main schedule driver. We will start the construction of the distribution network as soon as possible; our conservative estimate is April 1, 2021. We have completed all path preparation projects except Warner Hill Road, which should be complete in November. Construction of the network equipment room is complete; electronics could start being installed later this year. The project remains on budget. The first tranche of town borrowing for $500,000 is expected to close on November 10, 2020.