Category: Make-Ready

Information about Charlemont Connect make-ready. Make-ready is work to prepare a “path” for the distribution network to run throughout the town. Most of this work is done by the utilities (National Grid and Verizon) to make space on existing utility poles. In some cases, the town may perform make-ready work by installing new underground conduit (e.g. near the town hall or on Hawk Hill Road) or new utility poles (e.g. on the west end of Tower Road) to create a cost-effective path for the distribution network.

Burke Electric Selected for Warner Hill Utility Pole Installations

Charlemont’s Highway Department dug some test holes that uncovered ledge at the proposed pole locations on Warner Hill Rd. Our partners, Westfield Gas & Electric (WG&E), selected Burke Electric because they have the experience and needed equipment for setting utility poles in areas with ledge.

Comments closed

Warner Hill Road Poles Supported By Select Board and Residents

The underground utility path on Warner Hill Road is being modified with resident, Highway Superintendent, Broadband Committee, and Select Board support. Concerns about the originally designed fully underground solution are being addressed by adding two new utility poles. Danek Excavating is expected to complete the work in late summer and early fall.

Comments closed

2020.08.30 Select Board Update

Charlemont Municipal Fiber Network
Selectboard Status Report
August 30, 2020

Summary

Verizon has approved two licenses (out of 17) but the estimated final completion date is still December 31, 2020. This is the main schedule driver. Based on this date, we anticipate starting construction of the distribution network in April, 2021. We are working to complete several “path preparation” projects:  Heath Stage Terrace is complete. National Grid was granted approval to install new utility poles along Hawk Hill Road, eliminating the need for the town to install underground conduit there. The new utility poles have been installed along Tower Road; tree trimming is being scheduled. Design adjustments on Warner Hill require a pole hearing which is scheduled for September 8. Construction of the network equipment room is complete; electronics could start being installed later this year. So far, the project remains on budget. We are anticipating the first tranche of town borrowing in September, 2020.

Comments closed