2020.08.30 Select Board Update

Charlemont Municipal Fiber Network
Selectboard Status Report
August 30, 2020

Summary

Verizon has approved two licenses (out of 17) but the estimated final completion date is still December 31, 2020. This is the main schedule driver. Based on this date, we anticipate starting construction of the distribution network in April, 2021. We are working to complete several “path preparation” projects:  Heath Stage Terrace is complete. National Grid was granted approval to install new utility poles along Hawk Hill Road, eliminating the need for the town to install underground conduit there. The new utility poles have been installed along Tower Road; tree trimming is being scheduled. Design adjustments on Warner Hill require a pole hearing which is scheduled for September 8. Construction of the network equipment room is complete; electronics could start being installed later this year. So far, the project remains on budget. We are anticipating the first tranche of town borrowing in September, 2020.

Comments closed

National Grid Supports Hawk Hill Rd. Path Preparation

National Grid will be replacing the underground electrical service on a portion of Hawk Hill Road with an aerial solution. At a pole hearing on August 24, National Grid received Select Board approval for the poles to be placed in the road right of way. Once complete, National Grid will allow the Charlemont municipal fiber network to use these poles for the fiber optic cable.

Comments closed

Warner Hill Road Path Preparation Project Kicks Off

Tom Danek of Danek Excavating met on-site with Charlemont’s Highway Superintendent, Gordon Hathaway, and Broadband Chair, Bob Handsaker to discuss the installation path of new conduit on a section of Warner Hill Road. This early communication will support the future maintenance of both the roadway and the municipal broadband network.

Comments closed