2020.11.01 Select Board Update

Charlemont Municipal Fiber Network
Select Board Status Report
November 1, 2020

Summary
Verizon has now approved 14 licenses (out of 17), with just a few poles left on the other applications. This remains the main schedule driver. We will start the construction of the distribution network as soon as possible; our conservative estimate is April 1, 2021. We have completed all path preparation projects except Warner Hill Road, which should be complete in November. Construction of the network equipment room is complete; electronics could start being installed later this year. The project remains on budget. The first tranche of town borrowing for $500,000 is expected to close on November 10, 2020.

Comments closed

Burke Electric Selected for Warner Hill Utility Pole Installations

Charlemont’s Highway Department dug some test holes that uncovered ledge at the proposed pole locations on Warner Hill Rd. Our partners, Westfield Gas & Electric (WG&E), selected Burke Electric because they have the experience and needed equipment for setting utility poles in areas with ledge.

Comments closed

Warner Hill Road Poles Supported By Select Board and Residents

The underground utility path on Warner Hill Road is being modified with resident, Highway Superintendent, Broadband Committee, and Select Board support. Concerns about the originally designed fully underground solution are being addressed by adding two new utility poles. Danek Excavating is expected to complete the work in late summer and early fall.

Comments closed