August 31, 2019
Summary
Project schedule still has considerable uncertainty. We hope to be operational by the end of 2020, but this is depending on the utility make-ready schedule. The project is generally on budget. As of the end of August, $186,380.50 has been expended out of the state grant funds, but the bulk of the make-ready expenses will start to be paid in September and we may need to start doing some limited borrowing to cover these expenses. We are meeting with Unibank on September 4. A construction contract for the network hub room has been awarded. Permitting and procurement for other parts of the distribution network are underway (town hall exterior, Hawk Hill Road, Heath Stage Terrace, west end of Tower Road, east end of South River Road).