Our distribution network contractor, TriWire, has completed the Chickly River crossing in FSA 02! There remains one more Deerfield River crossing at Shunpike in FSA 02, expected to be completed this month.
FSA 05 remains in the testing phase this week and splicing has not yet begun in FSA 04 due to a shortage of available splicers. Charlemont is working with the TriWire team to source additional contractors. Once the testing is complete in FSA 05, the splice crews will move into FSA 04. FSA 05 will have a two-week validation period and will become activated for service following any needed remediation.