Charlemont Municipal Fiber Network, Selectboard Status Report, May 9, 2020
Summary
Make-ready is in progress with National Grid. We selected the contractor for construction of our distribution network and received the next grant milestone payment of $185,500 from EOHED.
Verizon extended their estimated make-ready completion date for the town and we are now anticipating starting construction of the distribution network in April, 2021. We plan to complete four “path preparation” projects this summer. Three underground conduit projects are out to bid (Hawk Hill Road, Heath Stage Terrace, Warner Hill Road). We believe we finally have a resolution for the railroad crossing near Long Bridge via a public-way crossing at Route 8A. This will incur additional make-ready costs, but we believe they will be reimbursed by the state. Construction of the network equipment room in the basement of the town hall has resumed. So far, the project remains on budget and we are planning for town borrowing in FY21.