Quotes rejected for Hawk Hill Rd. and Heath Stage Terrace Conduit

The town received quotes from two bidders. Both of the quotes exceeded the estimated cost of the work through an intergovernmental agreement with Westfield Gas & Electric. As a result, the town decided to decline all of the quotes at this time.

Comments closed

2019.08.31 Select Board Update

Charlemont Municipal Fiber Network
Selectboard Status Report
August 31, 2019

Summary

Project schedule still has considerable uncertainty. We hope to be operational by the end of 2020, but this is depending on the utility make-ready schedule. The project is generally on budget. As of the end of August, $186,380.50 has been expended out of the state grant funds, but the bulk of the make-ready expenses will start to be paid in September and we may need to start doing some limited borrowing to cover these expenses. We are meeting with Unibank on September 4. A construction contract for the network hub room has been awarded. Permitting and procurement for other parts of the distribution network are underway (town hall exterior, Hawk Hill Road, Heath Stage Terrace, west end of Tower Road, east end of South River Road).

Comments closed

Town Hall Exterior Conduit Excavation and Installation RFQ Available

The Town of Charlemont will accept price quotes for the excavation/ installation of broadband conduit on the exterior of the Charlemont Town Hall.

Price Quote should be marked “ TOWN HALL EXTERIOR EXCAVATION/ CONDUIT INSTALLATION ” and will be received by the Charlemont Broadband Committee, 157 Main St., P.O. Box 677, Charlemont, MA 01339 until September 23, 2019, at 2 pm. Quotes may be emailed.