2019.04.15 Status Update

Charlemont Municipal Fiber Network, Selectboard Status Report, April 15, 2019

Summary

Project schedule still has considerable uncertainty, but hoping to be operational by the end of 2020.

Project is on budget, $184,211.85 has been expended to date out of the state grant funds.

We are currently focusing mainly on three areas of the project: utility make-ready work, finalizing critical aspects of the plan for the distribution network and construction of the network hub room in the town hall basement.