Testing teams will begin in FSA 04, East Charlemont, on December 16! Dedicated crews from ITG Communications will be testing the network, estimated to take 2-4 weeks for this FSA. Once this step is complete there is a period of desktop validation and then the area can be released for service installation.
Splicing continues steadily in FSA 02 with good progress through West Charlemont. Teams will pause for a holiday break but are committed to Charlemont until the work is complete. Testing teams will be deployed to begin testing in FSA 02 as soon as the work is finished in FSA 04.
Construction teams hanging fiber and MSTs are wrapping up work in town with FSA 03. Splicers will move into this area once the construction is complete.