Skip to content

TriWire Selected As Distribution Network Construction Firm

Last updated on July 29, 2020

TriWire has been selected to build Charlemont’s municipal fiber distribution network. As the lowest qualified bidder, the team at TriWire will begin construction on the town’s fiber-optic backbone as soon as our Make-Ready work is complete. The construction bid is very close to our initial estimates as the project continues to come in on budget.

Despite the COVID-19 pandemic, National Grid projects the completion of our Make-Ready is on schedule, however, Verizon’s Make-Ready completion date has been extended an additional 60 days. The Make-Ready phase of the project will continue to be the most uncertain since the utility companies schedule and perform this work based on independent internal timelines.