Last updated on March 4, 2021
TriWire, our distribution construction team, has the fiber for each FSA running into our network equipment room ready to be connected to the installed optical equipment! Because our Network Equipment Hub is in the center of the traffic calming area, having the network backbone run through to the hub is another success for the project staying ahead of the Department of Transportation in the village center.
Working through snow and pandemic, the construction crews and the police details working on Route 2 since the beginning of February have accelerated the build through the village. Please give them a shout-out – socially distanced of course – to say thanks!